Guide: Withdraw/Deposit with Centralized Exchanges (EVM) ​

This guide is a walkthrough on how to deposit to/withdraw from $NIBI-supported centralized exchanges via EVM.

  1. How to Buy NIBI on an Exchange
  2. How to Send NIBI from the Web App to a CEX like MEXC, Kucoin, Bybit, or Gate.io
  3. Withdrawing from Centralized Exchange to EVM
  4. Depositing to Centralized Exchange from EVM

How to Buy NIBI on an Exchange ​

How to Send NIBI from the Web App to a CEX like MEXC, Kucoin, Bybit, or Gate.io ​

Withdrawing from Centralized Exchange to EVM ​

1 | Head to the Nibiru Web App and connect your EVM wallet.

2 | Click the EVM address and copy the NIBI derivation of your EVM wallet.

3 | Head to the CEX and use the copied address as the withdrawal address and follow the exchange instructions. No memo/tag is needed.

4 | Upon confirmation, your funds will arrive and display in your EVM wallet.

Depositing to Centralized Exchange from EVM ​

1 | Create an IBC Wallet.

2 | Head to the Nibiru Web App and connect your EVM wallet with the $NIBI funds to be deposited, as well as your IBC wallet.

3 | With both wallets connected, click the NIBI address and copy the EVM derivation of your IBC wallet.

4 | With the EVM derivation of your IBC wallet copied, send over your $NIBI from your EVM wallet using the copied address as the destination address. You can do this in your EVM wallet directly, or using the web app, as shown below.

5 | Once funds have arrived in your IBC wallet, using either your IBC wallet directly or using the web app (shown below), deposit your funds to the exchange deposit address.

6 | Upon confirmation, your funds will arrive and display in the exchange.